|
|
INVESTIGATIONS RELATING TO SEEPAGE THROUGH A NATURAL SIDE EMBANKMENT FOR A RESERVOIR PROJECT
Heigerth Günther
Technical University Graz, Dep. of Hydraulic
Structures
Stremayrgasse 10, A-8010 Graz / Austria
Tel.: 0043-316-873-8360, Fax: 0043-316-873-8357,
E-mail: heigerth@kwb.tu-graz.ac.at
Abstract
Seepage through reservoir slopes to a neighbouring valley may involve serious problems. For a hydro project in southern Turkey (Client DSI/Ankara, Consultant chaired by Verbund-Plan/Vienna), it was necessary to investigate an unfavourably bedded flysh "side embankment" showing slide scars, which forms one of the reservoir slopes. A large number of in-situ and laboratory investigations were carried out to obtain information on the hydro-geological and geotechnical details. Using a mathematical model, underground flow patterns and pressures were analysed using the potential method, and the sliding stability of the downstream slope was analysed assuming a variety of different characteristic values and engineering measures. This led to a proposal providing for a grout curtain and a drainage curtain as well as a monitoring system, which would ensure the required safety and allowed adjustment during operation.
Keywords: Seepage,
Hydro-geology, Slope stability, Potential method, Reservoir
embankment
1. Introduction
Among the main elements to be considered in the design of a dam are
hydraulic questions such as seepage through the abutments and the appropriate
engineering measures to be taken. In addition, depending on the topography and
morphology of the reservoir area, seepage through the reservoir slopes to
adjacent valleys may pose a major problem. Special attention must in this case
be given to slope stability at the point of emergence of seepage flow. The following
is a report on a project where seepage through a "natural" embankment adjacent
to the abutment of a fill dam had to be studied with a view to developing
measures for slope stabilisation and monitoring.
The Turkish overall development plan for central and eastern Anatolia in
the early eighties included investigating the Seyhan river basin for potential
utilisation. The master plan provided for 7 multi-purpose stations serving for
irrigation, flood control, and power generation. The client was Turkish General
Directorate of State Hydraulik Works DSI (Devlet su isleri); the design studies
were carried out by a joint venture consisting of sponsor Verbund-Plan/Vienna,
Romconsult/Bucharest, and Temelsu/Ankara. Meanwhile the lowest plant has been
constructed.

Fig. 1
Plan view of Yedigöze project (showing planned measures)
One of the next plants to be realised is another storage development
("Yedigöze"): A more than 100m high rockfill dam with an earth core will create
a reservoir with a total storage of 660 hm³ (see fig. 1, Plan view). The
spillway, designed for a discharge of 8760 m³/s, will be situated on the
right-hand bank. The left bank will accommodate the powerhouse with two tunnels
with a discharge of 194m³/s each as well as the diversion tunnels, later to be
converted to bottom outlets. The dam site has been found to afford optimal
overall conditions in both topographical-morphological and
geological-geotechnical terms. Situated on the outer side of a meander-like
river loop that follows the lines of the main geological structures, the
project has involved the need to study in some detail the mountain ridge
enclosed by the loop as part of the reservoir boundaries. So, following the
completion of the Feasibility Study, a work group under the direction of Prof.
W.Schober from Innsbruck university (Austria), in which the author
participated, prepared a study dealing with this problem.
2. Hydrogeological and
Geological Situation, In-situ Investigations
The river valley has been carved with medium steep slopes some 150 m
deep into a mid-Miocene flysch zone south of the Taurus mountains. The flysch
is characterised by alternating layers of calcareous sandstone and clay-stone.
The studied ridge is more than 2 km long and 750 to 1000 m wide at the base. It
mainly consists of thick-bedded sandstone with a bed thickness of several
metres, and intercalations of clay-stone. The bedding shows a fairly general
parallel dip to the south; the strike is approximately parallel to the slope.
The downstream slope exhibits major slide scars. The river valley itself is
filled with alluvial material.
Following first geological mapping carried out by DSI, core drillings
were sunk, mainly along a characteristic cross section, an exploratory gallery
was driven, and water pressure tests were carried out. This gave the following
picture: The slope shows evidence of extensive sliding at the surface. The
slide scars decrease with depth, so as to pass into the intact bedding-plane
slope of 8 to 12 %. Three levels were established where continuous clay-stone
layers consitute the active or potential sliding planes. The investigations
showed different permeabilities to exist in these sections, permeability
parallel to the bedding planes being naturally higher than that vertical to the
bedding planes. Further details completed the overall picture.
These findings suggested that reservoir filling might result in seepage
through the slopes, mainly parallel to the bedding planes. Due to the presence
of the less permeable clay layers, such seepage would risk to mobilise uplift
forces likely to destabilise major slope portions and cause slides at the
points of emergence of the seepage water. In order to obtain more details, rock
mechanics in-situ and laboratory tests were performed (by DSI and Middle-East
Technical University at Istanbul), in particular to establish residual shear
strengths and residual shear angles (27° - 23°).
The relevant department at Innsbruck university, carried out
complementary laboratory tests, which included permeability tests. The
sandstone was not found to show any major anisotropy of permeability; the
samples turned out to be surprisingly impermeable (K=10-9 - 10-10
m/s). Evaluation of the tests showed that the slide phenomena of the slope
could not be explained by underground joints and fissures alone. The presence
of fissure water pressure was suggested as a further main cause. In addition,
earthquake effects had to be considered.
3. Possible Preventive
Measures and Analytical Studies
In order to ensure the stability of the downstream slope after reservoir
filling and, as far as possible, to improve the conditions as compared with the
present situation, it is necessary to prevent the build-up of fissure water
pressures in the critical area. For this purpose, we had to investigate several
potential engineering measures and study and compare their effects in terms of
slope stability by analytical means. Thanks to the parallelism of the
geological situation it was possible to adopt a two-dimensional investigation
programme to be carried out along what was selected as the most unfavourable
slope cross section. For this purpose, the three above-mentioned series of beds
were defined by different characteristic numbers.Therefore, it appeared useful
to adjust a FEM grid to this geological structuring for both the flow and the
slide studies. Different ratios, varying from 1 : 1 to 100 : 1, were assumed
for the permeabilities parallel and vertical to the dip of strata.
For calculating steady seepage flow with a free groundwater surface, we
used a program FEFLOW, assuming Darcy's law and complete saturation in the
groundwater zone, which means that it was possible to apply the potential
method. The results were plotted as flow nets (with potential lines and
velocity vectors) as well as fields of pressure lines; figs. 2a and 2b are
examples showing the result of one loading case analysis.

Fig. 2a Flow pattern -Orthotrope case (K-10:1) in 4 layers, with grout and drainage curtains

Fig. 2b Pressure lines - diagrammatic example showing layer structure and potential slip surfaces
For the slide studies, we defined for each case two slide masses of
different depths with their failure surfaces naturally in a bedding plane (fig.
2b). The exterior loadings were taken as the fissure water pressures obtained
from the flow analysis as well as- in additional loading cases - a quasi-static
earthquake acceleration. According to the usual practice, we determined the
minimum shear angle and defined the resistance to sliding as the quotient of
residual shear strength to minimum shear strength. Assuming prototype
conditions, however, the sliding resistance is definitely higher.
As preventive engineering measures we first suggested a grout curtain
with a realistic permeability equal to the lowest natural permeability as well
as a parallel drainage curtain in two different lengths. The following cases
were finally studied:
- no engineering measures (reference case)
- grout curtain (impervious), drainage
curtain, k =1 : 1 to 100 : 1
- grout curtain (partly pervious, k 50 times as large), k = 1 : 1 to
100 : 1
- grout curtain (partly ineffective), k = 100
: 1
The results were as follows:
In the first case, seepage flow, as expected, affects the areas
vulnerable to sliding; so this case is unacceptable.
All the other cases show that the fissure water level downstream of the
grout and drainage curtains is low enough to remain practically clear of the
critical areas. As expected, it is necessary to provide a drainage curtain as a
safety measure in case the grout curtain is only partly effective for technical
reasons. The flow that would enter the drainage curtain has been calculated to
range between about 14 and 37 l/sec x km, which would correspond to 88 - 93 %
of the total seepage flow.
The calculated resistance to sliding is slightly above 1 for the case
without preventive engineering measures, but is less than 1 on the assumption
of added earthquake effects. For the suggested measures and a partly permeable
grout curtain, we obtained 2.03, and 1.42 assuming earthquake effects, as most
unfavourable values. On the extremely pessimistic assumptions, these values can
safely be considered as sufficient.
4. Conclusions and Planned
Preventive Measures
The engineering measures to be considered will necessarily be a
combination of grout curtain and long drainage curtain. The system developed is
shown in fig. 3:

Fig. 3 Typical profile - Grout and drainage system including monitoring system
·
Sink a grout
curtain along the crest, determining the respective depths, by individual
sections, from preceding investigations. Grouting pressures will be selected as
a function of depth, no subsequent near-surface pressure grouting under
surcharge being needed. This systematic grouting should naturally be
supplemented by grouting as required for geological reasons.
·
Downstream, two
tunnels will be provided from which a not more than two-level drainage curtain
will be sunk. The two tunnels should be provided with a longitudinal slope and
one access and drainage gallery each. The curtain, in particular with respect
to borehole spacing, can be selected to suit the local conditions. Grout
curtain and drainage curtain connect with the corresponding structures in the
abutment of the fill dam and should extend sufficiently far into the area
outside the region of the loop.
·
This scheme
might prove redundant in the light of further details being obtained or in the
course of the construction operations and should be adjusted, and thus possibly
be reduced, as the work proceeds. Supplemental measures should be taken on the
downstream slope surface
·
A measuring
and monitoring system is planned to form an integral part of the scheme.
This consists mainly of piezometers arranged at several cross sections and
installed from the two tunnels. Furthermore, the scheme provides for drainage
channels equipped with instruments measuring the entering seepage flows.
Naturally, total flow has to be measured at the portal. At least those values
should be recorded continuously and should possibly be included in an alarm
system. Furthermore, the two access galleries offer the possibility of
installing simple measuring equipment to detect potential sliding. This
monitoring system can be supplemented as required by geodetic and other aboveground
and underground measurements.
Measuring and monitoring will have to be particularly intensive during
the phase of first filling. This will at the same time allow comparison with
the analytical results and calculation of the actual seepage conditions.
A main idea in our concept has been the possibility of supplementing even in the long term the
preventive measures as experience is gathered during operation. This mainly
refers to the provision of additional drainage holes, which could probably be
sunk without interference with reservoir operation.
By way of summary, it can be stated that a solution has been found to a
fairly unusual problem, affording the required safety even if allowance is made
for the variance of the natural parameters. Monitoring and the possibility of
subsequent supplementary measures are to ensure that this safety is a lasting
one.
Reference:
Republic of Turkey, General Directorate of State Hydraulic Works:
Yedigöze, dam and hydroelectric power plant project;
Special Study: Left bank seepage and landslide problems 1984 (not
published).