|
|
A COMBINED STORM OVERFLOW STRUCTURE: DESIGN
PROCEDURE
GIUSEPPE OLIVETO, MAURO
FIORENTINO, and GIANLUCA MININNI
DIFA, University of
Basilicata
I-85100 Potenza, Italy
Phone: +39 971 474676; Fax:
+39 971 56537; e-mail: fiorentino@unibas.it
Abstract
In combined sewer systems suitable locations are
selected where only a fraction of the maximum discharge is allowed to continue
towards the sewage treatment station. To this purpose, overflow structures are
used. In this paper a storm overflow structure constituted by a sideweir and a
bottom opening is proposed. It
is particularly suitable for subcritical approach flows. A hydraulic design
procedure is described and, based on systematic observations and by using
governing flow equations, the main hydraulic features are specified. The
results reveal that the proposed overflow structure has advantageous
characteristics with reference to efficiency, reliability, and maintenance.
Keywords: Sewers,
storm overflow structure, sideweir, bottom opening, hydraulic performance.
Introduction
Storm overflow structures are key devices in combined sewers. For
discharges up to the design discharge of the sewage treatment station no
overflow should occur. Whereas, the discharge exceeding the so-called critical
treatment discharge should be conveyed towards a storage basin or a receiving
water body.
Over the last decades two standard designs have been favoured: sideweir
and bottom opening. Side weirs are exclusively adopted for subcritical approach
flows; bottom openings are particularly suitable for supercritical approach
flows.
With reference to sideweirs, those of high weir height are needed for an
overflow structure alone, whereas the combination with an overflow chamber can
involve also sideweirs of medium or low weir height. An acceptable efficiency
of a sideweir of high weir height can be obtained by locating a Venturi flume
and/or a sluice-gate slightly downstream the end of the weir (Biggiero, 1969);
that, however, can involve small velocities close to the weir and, thus, deposition
can occur. Vice versa sideweirs of medium or low weir height require little
maintenance, but their efficiency is poor (Biggiero et al., 1994).
Based on the foregoing considerations, in this paper a storm overflow
structure constituted by a sideweir and a bottom opening is proposed in order
to improve the efficiency of sideweirs of low weir height.
The hydraulic scheme
The proposed overflow structure is constituted by a prismatic sideweir
of low weir height and a bottom outlet located slightly downstream the end of
the weir. A similar device was also mentioned in Biggiero (1969). The approach
flow is subcritical or close to critical flow. For discharges up to the
critical treatment discharge no lateral outflow occurs; thus, all discharge
passes through the outlet and continues towards the sewage treatment station.
For the maximum discharge, usually much larger than the critical treatment
discharge, the sideweir determines the transition from sub- to supercritical
flow slightly upstream the inlet section, so that the flow along both the weir
and the bottom outlet is supercritical. The discharge that passes through the
outlet continues towards the sewage treatment station, the remainder and the
lateral outflow are conveyed towards a storage basin or a receiving water body.
More details on the proposed device are reported in Fiorentino et al. (1998).
Hydraulic design
Fig.1 shows a definition sketch with h = flow depth, Q = discharge, D =
diameter, l = length, c = height, w = width, subscripts o, e, and d referring
to approach, end, and downstream sections, respectively, and subscripts sw, and
bo referring to sideweir, and bottom opening, respectively. The end section is
so-called in relation to the end section of a pipe discharging into the
atmosphere. For subcritical approach flow ho will denote the
critical depth.

Fig.1
Definition of flow: (a) plan; (b) side view
Designing the proposed overflow structure is controlled by two
discharges: (a) critical discharge to sewage treatment station for which there
is just no lateral outflow; (b) maximum discharge usually much larger than (a).
Case (a) determines the structure geometry, and case (b) has to be verified for
excess treatment discharge.
Geometric
characteristics
Referring to the critical treatment discharge, the structure geometry
may be determined as follows:
The weir length lsw should be assumed equal to 4D. In fact,
this length provides a good compromise
between efficiency and compactness of sideweirs of low weir height;
The weir height csw should be equal to the approach flow
depth ho;
The width wbo of the bottom opening should be equal to the
approach surface width;
The length lbo of the bottom opening should be determined
from the following equation (Oliveto et al., 1997a)
(1)
where Fo is the approach Froude number (equal to 1 for
subcritical approach flow).
Thus, for a given weir height the bottom opening geometry is completely
defined.
Overflow discharge
Assuming that the influence of the bottom outlet on the outflow process
along the weir is negligible, the overflow discharge may be predicted by
applying equations relative to sideweir and bottom opening. Thus, referring to
the maximum discharge and for given both approach flow conditions and overflow
structure geometry, the following procedure may be applied:
The lateral outflow Qo - Qd,sw should be
determined by the equation (Oliveto et al., 1998)
(2)
in which the coefficients
and
are given by
(3)
(4)
Eq. (2) may be used provided that: 1£ lsw/D £ 6, 0.1£ csw/D £
0.25, and 0.35£ ho/D £ 0.70. All these conditions assure
supercritical sideweir flow, i.e. no hydraulic jump occurs along the weir
(Sassoli, 1963).
Consequently, the downstream discharge Qd,bo should be
determined by using the average discharge equation (Biggiero, 1969; Oliveto et
al., 1997b)
(5)
In particular, the approach flow depth h, assumed equal to hd,sw,
can be determined by the following theoretical equation (Oliveto et al., 1998)
(6)
and the average discharge coefficient Cda can be determined
by either the equation (Biggiero, 1969)
(7)
or the equation (Oliveto et al., 1997b)
(8)
where the approach flow depth h and the approach Froude number F can be
assumed equal to the flow depth hd,sw and the Froude number Fd,sw
at the end of the weir, respectively.
EXPeriments
experimental
SETUP
The tests were conducted with a Plexiglas pipe of internal diameter D =
192 mm inserted in a rectangular channel 500 mm wide and 500 mm high. The
system observation was thus readily available from the existing channel. The
pipe length from the inlet section to the beginning of the sideweir was 2,100
mm. The pipe lengths from the end of the bottom opening to the outlet section
ranged between 4,155 and 4,100 mm according to the bottom opening length. The
invert of the pipe was 200 mm above the channel bottom. In the stilling zone
between the upstream channel end and the pipe inlet, pressure heads were up to
480 mm. The approach
flow in the pipe was stabilized by a flow straightner inserted at the pipe inlet section and made of
pulled PVC pipes with 14 mm internal diameter and length 192 mm. In order to
further regularize the flow in the pipe, the inlet flow depth was adjusted by a
Polystyrene sheet.
Four configurations were used. The transverse section of the outflow
device was U -shaped. The relative length lsw/D of the sideweir was
always equal to 4 and the relative weir heights csw/D were 0.10,
0.15, 0.20, and 0.25. The weir crests were sharp and horizontal, and one-sided
outflows were considered. The beginning of the outlet was located 50 mm
downstream the end of the sideweir.
experimental
measurements
For each experiment the surface profile was taken to ± 1 mm accuracy. The approach discharge was
measured by an orifice meter provided Q > 10 ls-1. Deviations
were smaller than ± 2%. The discharge
across the bottom opening was rated with a mobile Venturi flume (Ueberl and
Hager, 1994) inserted below the tailwater pipe. Its accuracy was ± 2% - 3% due to some wave action set up by
the plunging jet.
experimental
observations
Some photographs are added to provide a description of the flow
characteristics.
The relative weir height csw/D of sideweir is 0.10, the
relative length lsw/D of bottom opening is 1.45·csw/D,
and the relative width bbo/D is 0.55.
Fig.2a shows a top view on the outflow structure for a case in which all
discharge flows through the opening. Figs. 2b to 2d refer to ho/D
nearly 50%. As it can be noted only a portion of the approach discharge passes
through the outlet. The flow is tranquil, and no surface waves may be seen
except downstream from the bottom opening. Although the sideweir is one-sided,
the feeble asymmetry of the flow can be confidently neglected.


Fig.2
Photographs of experimental stand.
(a) view on outflow structure for h0 < cSW;
(b) downstream view to the sideweir flow (the stability of the approach
flow surface an be recognized;
(c) view on bottom opening;
(d) Plexiglas sheet to separate the lateral outflow from the outlet
discharge.
Analysis of data
sideweir
End depth
From the experiments, all characterised by values of ho/D
ranging between 0.40 and 0.60, the following equation was obtained
(9)
according to observations made by Biggiero et al. (1994) on one-sided
weirs with low or medium weir height.
sideweir
DOWNSTREAM depth
For given parameters ho, hd,sw, Qo, and
Qd,sw one may define the downstream depth ratio Yd,sw = hd,sw/ho
and the discharge ratio Rsw = Qd,sw/Qo.
Compared to the data obtained determining Rsw by Eq. (2) and Yd,sw
by observations, the theoretical curve Yd,sw (Rsw) from
Eq. (6) was found somewhat low (-5%) which must be attributed to the simplified
approach. Eqs. (2) and (6) give thus an acceptable estimate of Yd,sw,
although referred to sideweir alone. Based on the foregoing results, the
assumption that the interaction between the sideweir and the outlet is
negligible can be retained reasonable.
discharge
across the bottom opening
Regarding to the outlet discharge Qd,sw - Qd,bo,
the following empirical curve was found
(10)
where Rsw is given by
Eq. (2). Thus, based on Eqs. (10) and (2) the hydraulic performance of the
proposed overflow structure can be easily determined. To this purpose, the
procedure based on Eqs. (2) to (8) can also be used with reasonable accuracy.
Defined by [(Qo -Qd,sw) + Qd,bo]/Qo
the efficiency of the proposed overflow structure and by (Qo -Qd)/Qo
the efficiency of sideweir alone, one finds, by applying the above equations,
that the efficiency of the proposed overflow structure is much higher than that
of sideweirs with a low or medium weir height, and comparable with that of
sideweirs with a high weir height.
Conclusions
A storm sewage overflow constituted by a sideweir of low weir height and
a bottom outlet just downstream the weir was studied. This structure is
suitable for combined sewer systems with subcritical approach flows and
requires a limited maintenance.
By using empirical and theoretical equations referred to sideweir or
bottom opening the hydraulic design criteria are specified.
Moreover, based on model observations the following information were
deduced:
- the influence of the bottom outlet on the outflow process along the
weir is negligible;
- the discharge that passes through the outlet and continues towards the
sewage treatment station may be easily determined by Eq. (10).
By applying Eq. (10) one can also demonstrate that the efficiency of the
proposed outflow structure is much higher than that of sideweirs of low weir
height and comparable with that of sideweirs of high weir height.
References
Biggiero, V. (1969). Scaricatori di piena per fognature. Criteri di
progettazione. Ingegneri, Naples, Italy, 57: 1-36 (in Italian).
Biggiero, V., Longobardi, D., and Pianese, D. (1994). Analisi sperimentale del comportamento
idraulico degli sfioratori laterali a bassa soglia. Giornale del Genio Civile, 132(3): 183-199 (in
Italian).
Fiorentino, M., Oliveto, G., and Mininni, G. (1998). A
storm overflow structure constituted by a sideweir and a bottom opening.
Submitted to Journal of Irrigation and Drainage Engineering, ASCE.
Oliveto, G., Biggiero, V., Fiorentino, M., and Hager, W.H. (1997a). Sul
processo d'efflusso da luci di fondo in reti drenaggio urbano. Atti delle
Giornate di studio in onore del prof. Edoardo Orabona, Bari, Italy, (in Italian).
Oliveto, G., Biggiero, V., and Hager, W.H. (1997b). Bottom outlet for sewers. Journal of Irrigation and Drainage Engineering, ASCE, 123(4): 246-252.
Oliveto, G., Biggiero, V., and Fiorentino, M. (1998). Hydraulic features of
supercritical flow along prismatic side weirs. Submitted
to Journal of Hydraulic Research.
Sassoli, F. (1963). Ricerca sperimentale sugli sfioratori laterali in
canali a sezione circolare. Parte seconda: andamento e tracciamento dei profili
liquidi. Atti VIII Convegno di Idraulica e Costruzioni Idrauliche, Mem. A-12,
Pisa, Italy:
1-18 (in Italian).
Ueberl, J., and Hager, W.H. (1994). Mobiler
Venturikanal im Rechteckprofil. Gas - Wasser - Abwasser, 74(9): 761- 768 (in German).