PHYSICAL MODEL STUDY FOR THE INTAKE CHANNEL AT THE SUBIYA POWER STATION, KUWAIT

 

JEN-MEN LO and A. AL-SALEM

 

Hydraulics and Coastal Eng. Dept., Environmental and Earth Sciences Division

Kuwait Institute for Scientific Research, P.O. Box 24885

13109-Safat-Kuwait

 

 

ABSTRACT

To identify and correct the objectionable features of the entrance shapes suggested by the conceptual design, three proposed arrangements for the intake channel of the Subiya Power Station in Kuwait were studied using physical models. The intake channel was designed to carry a maximum water supply of 148 m3/s with a maximum velocity of 0.16 m/s associated with the minimum design water level. This velocity value was calculated so that no resuspension of sediment already settled in the channel would occur and to avoid scouring of the channel banks. The model was designed according to the Froude similarity criterion as an undistorted model with a linear scale of 1:80. The model was constructed to simulate an area of 2460 x 1250 m. This area was found to be sufficient to run the model with a negligible boundary effect. The model test was carried out in the Hydraulics and Coastal Engineering Laboratory at the Kuwait Institute for Scientific Research. The main objective of the model test was to attain uniform velocity distribution inside the channel and to minimize separation of flow at the channel entrance. Based on the model study, it was concluded that the proposed bell-mouth intake channel should be modified by constructing 14 guide vanes at the entrance section to meet the required flow and sediment conditions.

 

Keywords: Hydraulic structure, Intake channel entrance, Sediment deposition, Cooling water, Tidal current.

 

INTRODUCTION

The Ministry of Electricity and Water, Government of Kuwait, is planning to construct a large complex of steam power and desalination plants on the Subiya Peninsula (Dames and Moore, 1983). Fig. 1 shows the location of the proposed Subiya Power Station. It is intended that the construction of the Subiya Power Station be executed in two stages. During the first stage, a power capacity of 2400 MW and a capacity for producing drinking water of 12 MIGD will be installed. The total cooling water demand for full-load operation during this stage will be 100 m3/s. During the second construction stage, the drinking water production will be increased to 96 MIGD. Accordingly, the final cooling water demand will be 148 m3/s. The cooling supply is from the seawater at Khor Al-Subiya (Fig. 1). The wastewater will be discharged into Kuwait Bay (Fig. 1).

 

 

Fig. 1. Location Map.

 

In the conceptual design, three intake arrangements were proposed to convey seawater from the Khor Al-Subiya to the power plant. Fig. 2 shows the three proposed intake arrangements. They were

 

 

Fig. 2. Three proposed arrangements for the intake channel.

 

1. A channel of 160-m bed width and 1:5-side slope guided by two straight dams extending across the Khor Al-Subiya to a contour of -4.0 m Kuwait land datum (KLD). The bed level of the channel is -6.5 m KLD, and the top elevation of the guide dams is +6.0 m. This was considered the basic solution.

2. A channel similar to the basic solution, but with a protruding southern guiding dam to minimize excessive separation of flow at the channel entrance.

3. A channel with a bell-mouth entrance that may allow for streamlined flow at the entrance and a more uniform flow inside the channel.

 

To identify and correct the objectionable features of the entrance shapes suggested in the conceptual design, the three proposed arrangements for the intake channel of the Subiya Power Station were studied using undistorted physical models. The intake channel was planned to carry a maximum discharge of 148 m3/s with a maximum velocity of 0.16 m/s associated with the minimum design water level. The velocity was calculated so that no resuspension of sediment already settled in the channel would occur and to avoid scouring of the channel banks. Four flow conditions were found to be critical for the hydraulic design of the channel entrance: the minimum water level of -1.5 m KLD associated with slack current, the maximum water level of +4.2 m KLD associated with slack current, and the mean water level of +2.0 m KLD associated with flood and ebb currents (Abou-Seida and Lo, 1987). The main objectives of the model test were to reach uniform velocity distribution inside the channel and to minimize separation of flow at the channel entrance.

 

MODEL LAWS

The model was designed according to the Froude similarity criterion as an undistorted model with a linear scale of 1:80. This scale was chosen to avoid the effects of surface tension and to ensure that the flow in the model was turbulent. The Froude similarity gave the following relationships: model length to prototype length = 1:80, model velocity to prototype velocity = 1:8.94, and model water discharge to prototype discharge = 1:57243.34.

 

MODEL CONSTRUCTION

The model was constructed to simulate an area of 2460 x 1250 m. This area was found to be sufficient to run the model with a negligible boundary effect. The model was constructed in the Hydraulics and Coastal Engineering Laboratory at the Kuwait Institute for Scientific Research (KISR) on a steel platform using lightweight material (styrocrete) covered with a 2-cm cement mortar apron. The supply and drainage systems were designed to simulate flood and ebb conditions; thus the flow ran from one side of the Khor to the drain at the other side for flood cases and vice versa for ebb cases. The water was supplied through a perforated pipe and flowed over an adjustable weir to the drainage channel. Plastic perforated boxes were arranged in front of the pipe to dissipate the excess flow energy and to help attain the required velocity distribution in the Khor. The intake channel was constructed across the Khor, and the intake flow was discharged through four pipes by gravity and adjusted by regulating valves. Dye and floats were used for velocity measurements. Fig. 3 shows the general arrangement of the model.

 

 

Fig. 3. General arrangement of the model.

 

EXPERIMENTAL RESULTS

A base test was run for an intake channel 1150 m in length with straight guide dams, and it was found that the most critical flow conditions were at a water level of +2.0 m KLD with flood and ebb currents. Backflow was noticed, and the nonuniformity of the velocity distribution inside the channel was clear.

 

The three proposed entrance conditions shown in Fig. 2a, b, and c were then tested for the +2.0-m KLD water level for flood and ebb cases. For flood and ebb cases in the first design (Fig. 2a), the flow was nonuniform, and backflow was observed along a great portion of the channel length. For the intake channel shown in Fig. 2b, the flow conditions were still unacceptable, and the nonuniformity of flow persisted in both the flood and ebb conditions. When the bell-mouth entrance (Fig. 2c) was used, a change in the flow behavior was noticed, and the flow started to be more uniform. But, separation at the entrance did not disappear, and backflow was noticed during both the flood and ebb conditions. Several measures were tried to attain a reasonable uniform distribution of the velocity as well as keep its value within the acceptable range for no resuspension of settled sediment. In addition these measures should have minimized flow separation at the entrance. The above requirements were reached by dividing the passage of the flow at the bell-mouth entrance into fifteen passages separated by fourteen piers each 14.4-m wide and 59-m long extending up to the +6.0-m KLD level. Fig. 4 shows the final arrangement for the proposed structures.

 

The velocity distribution was uniform and minimum separation was observed. The arrangement was then tested for a +4.2-m KLD water level with slack current and for a -1.5-m KLD water level with slack current. The experimental runs proved to be successful for these two cases. To prevent the oil slick movement, a series of tests for the final arrangement with the installation of skimmer walls between the guide vanes were also studied. The lower level of the skimmer walls was 1.5 m below the low water level (-1.5 m KLD), and the level is above the high water level (+4.2 m KLD). During the test, two different skimmer wall arrangements were installed. For the first arrangement, the skimmer walls were installed between the guide vanes, and for the second arrangement, the skimmer walls were installed between the guide vanes except at the openings of guide vane nos. 6, 7, 8, and 9. In general, with the installation of the skimmer walls, the flow pattern inside the intake channel obtained a uniform flow condition faster than in the case without skimmer walls.

 

CONCLUSIONS

It was concluded from the model study that the proposed bell-mouth intake channel should be modified by constructing 14 guide vanes at the entrance oriented at different angles to the channel is longitudinal axis. The spaces between the guide vanes are not equal, but depend on guide vanes' location at the entrance section. Modifications at the tip of the southern guiding dam is required (Fig. 4).

 

 

Fig. 4. Final configuration of the intake channel with 14 vanes at the entrance.

 

ACKNOWLEDGEMENTS

The "Physical Model Study for the Intake Channel at the Subiya Power Station, Kuwait" was accomplished through the joint efforts of the Ministry of Electricity and Water, Government of Kuwait, and the Kuwait Institute for Scientific Research.

 

REFERENCES

Abou-Seida, M. M. and Jen-Men Lo. 1987. Data for hydraulic studies

(Appendix B).Hydraulics studies and environmental impact assessment for the Subiya Power Station. Kuwait Institute for Scientific Research, Report No. KISR2371, Kuwait.

Dames and Moore. 1983. Hydraulic studies, Vols. II and III. Studies for Sabiya

area, Kuwait Bay, and development of electrical networks. Ministry of Electricity and Water, Kuwait, Government of Kuwait, Report No. MEW/CP/PGP/1113 80/81, Kuwait.