RESERVOIR SEDIMENTATION EFFECTS ON HYDROPOWER GENERATION - A CASE STUDY

 

Newton de Oliveira Carvalho

 

ELETROBRÁS, Centrais Elétricas Brasileiras S.A.

Rua da Quitanda, 196 - 22o andar

20091-000 - Rio de Janeiro, RJ - Brasil

Phone (021) 514-5430 - Fax (021) 516-4462

e.mail: newtonc@eletrobras.gov.br

 

 

ABSTRACT

The analysis of the existing hydroelectric power plants in Brazil shows that, in many cases, the sedimentological studies didn?t reach the adequate extension or weren?t even made. This procedure can be partially explained by the fact that 80% of the 53000 MW installed in hydroelectrics by 1991, including the total capacity of Itaipu, are concentrated in almost 20 power plants, the reservoirs volumes of which are bigger than 1000 hm3. With the perspective of building power plants with smaller reservoirs, the sedimentation problems must increase. In this paper the case of the Mascarenhas power plant, in the Doce river, ES, operating since 1974, is being analysed. The project of sedimentological studies of the reservoir was not included. It?s shown that the problems which occur nowadays could have been forecasted during the project study, if data and technology available on that occasion had been used. The results show the importance of making sedimentological studies before the dam construction.

 

Keywords: Sedimentology, Reservoir sedimentation, Hydrographic basin, Hydropower generation, Useful lifetime the reservoir, Sedimentometric network

 

INTRODUCTION

Brazil is a huge country presenting a surface area of 8 512 000 km2 with a population of about 150x106 inhabitants. Its surface is traversed by many rivers, including several important hydrographic basins. The Amazon, the biggest hydrographic basin in the world, covers more than half of the surface of Brazil, two thirds of its total catchment area. Most of the Paraná basin is located also in the country. The Paraguay basin (1 095 000 km2) has almost half of the area on brazilian territory. The Tocantins (757 000 km2) and the São Francisco (634 000 km2) basins are located entirely in the country. Other big basins, tributaries to the Amazon, are also entirely located in the country, as the Tapajós (490 000 km2), and the Xingu (504 300 km2). The total average water discharge of the brazilian rivers, which represents 8% of the sweet water available in the world, is of 257 790 m3/s [3]. One of the main uses of the brazilian rivers is for power generation, this representing 95% of the total generation in the country. The total hydropower installed by 1996 exceeds 53 000 MW, for a possible capacity of about 260 000 MW. In order to accompany the industrial development in the country, the electric sector is planning to install several hydropower plants in the next 15 years. Many reservoirs have been formed by the dams constructed for hydropower plants. There are more than 300 reservoirs, including those for small plants. However most of the hydraulic generation has been done by less than 20 hydropower plants with big reservoirs, each one of volumes higher than 1 000 hm3. The evaluated sedimentation time of these reservoirs shows a useful life time much longer than the economical useful lifetime of the plant. Probably due to this, the sedimentological studies on reservoir formation haven?t got enough importance. Another aspect of the problem is that until few years ago the rivers in the country presented a relative small sediment load, with an average value of less than 250 ppm. However, Brazil has several medium and small hidropower plants, presenting sedimentation in their reservoirs, which had the generation capacity reduced or completely interrupted [2]. For instance, the hydropower Funil, at the Contas river, had its operation interrupted from January/1992 to March/1993, presenting a loss of US$ 1 200 000. To recover its generation capacity it was necessary to dredge the sediment deposit near the intake at expenses of US$ 220 000. No previous references about sedimentological studies had been done for the reservoir. Although the dam was the bottom unloading type it was never in operation [1]. Another example is the hydropower plant Mascarenhas, on the Doce river, the dam construction of which was finished in 1974. Surprisingly in 1979 the reservoir was almost totally sedimentated. Due to this, generation is only possible nowadays by dredging every day near the intake. In the project, no references of sedimentological studies about the formation of the reservoir had been mentioned. This paper shows that the present problems at Mascarenhas could have been antecipated if a sedimentological study had been done before the formation of the reservoir, using data from other basins nearby.

 

A CASE STUDY

 

Characteristics of the Doce river basin

The catchment area of the Doce river (85 028 km2) is one of the most prolific sediment yielding in Brazil. The intense rains and the high slopes in the basin are the main natural causes for the high soil erosion in the region. As the main antropic causes there can be mentioned the mineral iron exploitation of the surface soil and the disforestation for getting wood coal for siderurgic purposes. By travelling in the region it is possible to see several eroded areas, presenting soils completely unprotected and slopes slippers along the roads [1]. The reservoirs formed by the basin and also the channels of the rivers are sedimentated. Every hydraulic construction in the river presents problems due to the high sediment load. Along all the water course of the Doce river and its tributaries the cities and properties have been seriously reached by the floods because the sedimentated channel cannot support any longer the volume of water. Almost all the sedimentated reservoirs in the rivers of the basin were formed for hydroelectric power plant as Brecha at the Piranga river, Peti at the Santa Bárbara river, Piracicaba and Sá Carvalho at the Piracicaba river, Salto Grande Complex at the Santo Antônio river, Bretas at the Suaçuí Pequeno river, Dona Rita at theTanque river, also Mascarenhas at the Doce river, and others. In spite of the ocurrence of so many problems, the studies didn?t make any reference to sediment transport nor recommendations for sediment control. The dam doesn?t have any structure to atenuate the sedimentation effects, as, for example, an unloading bottom [1].

 

The sedimentation problem

The hydropower plant Mascarenhas, of the ESCELSA, hydroelectric company of the Espírito Santo State, which was constructed on the low Doce river in order to generate 120 MW, has been operating since 1974. The dam has a height of 33 m and the location has a catchment area of 74 300 km2, corresponding to 88% of the total area of the basin. The water capacity of the reservoir at its maximum level is of 42,1x106 m3 and the dead volume is only of 8x106 m3. At Mascarenhas the river has an average of 927 m3/s of water discharge [1]. In 1979, after the big flood of February, 9th, with a water discharge of 14 000 m3/s, the reservoir was almost completely sedimentated. The sediment discharge in that wet year was of 30x106 t/year, more than half the capacity of the reservoir, considering a unit weight of 1,2 t/m3. But the reservoir was already sedimentated in the five previous years of high sediment load as computed later. The mud and sand transported by the river during the flood reached the intake easily and flowed through the intake to the turbines and equipments, causing operation difficulties for the power generation. The height of the sediment deposit near the dam achieved 27 meters, remaining a little more of 3,0m of water depth.

 

Present evaluation of the useful lifetime of the reservoir

Mascarenhas? small reservoir of 7 km length, presenting a lengthened shape, has a small trap efficiency of sediment. This permits the suspended sediment load to be discharged through the spillway and the intakes of water. So the planners of the dam had not worried about the reservoir sedimentation. They also forgot the fact that the bottom sediment load of the river couldn?t be discharged through the spillway, remaining in the reservoir. In order to evaluate the sediment discharge at that time, the planners could only get sediment yield data from measurements in the rivers of adjoining catchment basins because no entity had any sedimentometric networks in the Doce river before 1974, except for the station of Tumiritinga. The average values of water discharge and total sediment load were plotted to get the relation presented in Table 1 and Figure 1.

As can be seen the presented values are very scattered, giving a poor rating curve, due mainly the very few data.

 

The resulting equation

 

Gst = 25434 Q0,7722                                                                                     (1)

 

which gives for Mascarenhas a total sediment load of 5,0x106 t y-1, for a water discharge of 927 m3 s-1. It is not so far from the value at Tumiritinga, upstream of Mascarenhas, on the same river,  being a good value for the dam location.

 

River

Station

Period

Water discharge

Total sediment load

 

 

 

(m3 s-1)

(106 t y-1)

Santo Antônio

Ferros

1970/71

50

0,18

São Francisco

Porto das Andorinhas

1960/61

210

2,50

Pará

Porto Pará

1960/61

145

0,50

Paraopepa

Ponte da Taquara

1960/61

120

1,29

Indaiá

Faz. Bom Jardim

1960/61

46

2,05

Velhas

Várzea da Palma

1967/70

290

3,50

Borrachudo

Faz. Matinha

1960/61

190

0,51

Doce

Tumiritinga

1973/74

600

4,20

 

Table 1 - Total sediment load in catchment areas in the vicinity of the Doce river (measurements before Mascarenhas dam construction)

 

 

Figure 1 - Sediment transport curve obtained from data of adjoining stations of the Doce river

 

 

EVALUATION OF THE RESERVOIR SEDIMENTATION

The following equation can be used to compute the sediment load entering the reservoir each year:

 

                                                                                                                      (2)

 

which,

            S = annual volume of sediment entering the reservoir, in m3 y-1

            Gst = total sediment load, in t y-1

            t = trap efficiency of the reservoir

gap = apparent unit weight, in t m-3

 

The trap efficiency of the reservoir, using the Brune curve [4], shows a value near zero, meaning that Mascarenhas could dispose of all the sediment load by the spillway and conducts. However this is true for suspended sediment loads but not for the heavy coarse bottom sediment loads.

This coarse sediment load can have a value equal 2 to 150% of the suspended load [4]. Adopting 20% of the total, there results a value of 1.0x106 t y-1 for the bottom sediment load which remains in the reservoir. This value may represents a volume of 0,77x106 m3 y-1, considering an apparent unit weight for the coarse material equal to 1.3 t m-3.

As mentioned before, the reservoir capacity is equal to 42.1x106 m3 and the dead volume to 8.0x106 m3. Dividing the volume of bottom sediment load by this value there results a time of 55 years for total reservoir sedimentation and 10 years to sedimentate a volume equal to the dead volume.

These evaluated values don?t consider the high sediment load during floods, however they demonstrate that the useful lifetime of the Mascarenhas reservoir could be small for the planned lifetime of operation for power generation.

If this evaluation had been done before the dam construction a sediment control could have been done, by providing the dam with an unloading bottom.

 

CONCLUSION

The results show the importance of making sedimentological studies before the dam construction. Brazil doesn?t have a tradition in sedimentological studies due to not very high sediment loads in the rivers. However this is changing due to the crescent use of the soil as a consequence of the high population increase. For a near future several small and medium powerplants with the formation of their reservoirs are being planned. So, it is necessary to improve sedimentological studies in order to have better reservoir operation.

It is necessary to review the  basic sedimentometric network and install a secondary network. Nowadays the brazilian basic network is composed of less than 300 stations for suspended sediment measurements presenting a very poor frequency of operation. It is necessary to improve the frequency of measurement and to increase the number of stations. Also to get a better geographic distribution of the stations besides making bottom sediment load measurements.

The secondary sedimentometric network can be installed on the rivers on which it is planned to construct the dams. They may be operated only for a few years just to get enough data to make the local sedimentologic studies. Several others studies have to be made, as well as potential erosion investigation, for instance. These studies will indicate the procedures for sediment control in the basin, in the catchment area of the reservoir or even in the dam.

 

REFERENCES

1) ALMEIDA, Sérgio Barbosa, e CARVALHO, Newton de Oliveira (1993). Efeitos do assoreamento de reservatórios na geração de energia elétrica: análise da UHE Mascarenhas, ES. X Simpósio Brasileiro de Recursos Hídricos e I Simpósio de Recursos Hídricos do Cone Sul. ABRH. Gramado, RS. Brasil.

2) CARVALHO, Newton de Oliveira (1998). Assoreamento e proteção de reservatórios. VI Simpósio Nacional de Controle de Erosão. ABGE. Presidente Prudente, SP. Brasil.

3) DNAEE, Departamento Nacional de Águas e Energia Elétrica (1994). Disponibilidade Hídrica do Brasil. Brasília, DF.

4).OLD, International Commision on Large Dam (1989). Sedimentation Control of Reservoir. Guidelines. Paris, France.

5) STRAND, Robert (1974). Design of Small Dams. Sedimentation. US Bureau of Reclamation. Washington, DC. USA