|
|
MONITORING
GURI SPILLWAY PLUNGE POOL
ARTURO MARCANO
HID. Macagua I, San Felix, EDO. Bolivar,
Venezuela
Phone. 58-86-604208; Fax 58-86-604583; e-mail :
amarcano@edelca.com.ve,
ABSTRACT
The spillway of Guri Final Stage Project
located on the Caroni river in Southeastern Venezuela consists of three chutes
equipped with three radial gates per chute. Energy dissipation of the spilled
50m/s high velocity flow is achieved by discharging the flow jets into the air using flip buckets above the original gneiss granitic river bed where
residual energy is dissipated developing a plunge pool .Spillway operation and
plunge pool development has been closely monitored since 1979. 350.000 GWH of
energy has been dissipated and
400.000 m3 of rock has been
eroded in the pool. In this paper, an
analysis based on a number of
bathymetric soundings that were carried out
to measure the erosion process that has ocurred in the receiving pool is
presented together with estimates of
energy dissipated during the
period of operation in order to
evaluate stabilization of the pool.
Keywords: Spillway, Energy dissipation, Plunge pool,
Erosion.
INTODUCTION
The Final Stage of the Guri Hydroelectric
Project, Figure1, was completed in November 1986 as part of an expansion of the
original project. Installed power was increased from 2.054.000 to 10.000.000 Kw
by adding a second powerhouse equipped
with 10 Francis units. All structures including the 9 bays of the gated 30.000m3/s capacity
spillway were raised 55m to accomodate a new reservoir of 4250 km2
area and 1.11x1011 m3 water volume capacity . Significant
modifications were made to the original spillway which included raising
and redesigning the flip buckets
and provision for aeration devices. The
new spillway with a 140m head difference and a unitary discharge capacity of
250 m3/sxm started spilling in the wet season of 1987. Since then
the structure has operated for 605 days realeasing a total of 3.57x1011m3 of water. Energy dissipated in the
plunge pool in the period 1987-1997 amounts to 150.000 GWH. Operation
experience has been satisfactory in all respects. Preceding Guri Initial Stage
Project featured the same spillway unitary discharge capacity but working with
a 90 m head difference. Estimated energy dissipated during the period 1979-
1986 amounts to 200.000 GWH.
THE RECORD OF OPERATION
Following the commissioning of the first unit
of Guri Initial Stage Project in 1968, a very significant volume of water has
been spilled. Precise monitoring and recording of the spillway discharges has
been carried out since 1979 by EDELCA, the owner of the project. In 1979, the
expansion of the project was initiated and finalized in 1986. Expansion added
10 additional generators to the existing installed capacity and power
generation was increased gradually until 1992, when Guri Dam for the first time
achieved its project maximum energy of 48.000 GWH/year. As more energy was
generated by the two powerhouses, less flow was spilled. Table 1 summarizes the
record of operation of the spillway
before and after 1986 when the Final Stage
of the project was terminated. Discharge conditions have been varied
within this time period. In the 1979 -1986 time period the spillway operated an
average of 80 days/year with a normal head difference of 90m. Maximum specific
flow of 250 m3/sxm was sustained for 100 days in Chute 1, and 200 m3/sxm
were discharged by Chutes 2 and 3, sustained during 30 and 25 days ,
respectively. A total energy of 200.000 GWH was dissipated in the pool.
During the 1987-1997 time period, flow
was discharged at 140 m head difference; however, unitary flows and associated
power of the flow jet were reduced if compared with that observed in the previous time period. Yet ,
a total of 150.000 GWH of energy were dissipated and important changes in the
pool configuration were observed .
RESULTS OF THE SOUNDINGS
During the 19 years of monitoring 10 bathymetric surveys were carried out.
Original 90m head difference conditions developed an initial 10-20m deep, 250m
long plunge pool during the 1968-1978 time period of operation when 45° exit
angle- 6m submerged lip flip buckets were used. Since 1981, significant changes
were observed in the pool following
spillway operation with a more adequate 28-30° exit degree angle submerged-free lip flip
buckets. Extension and depth of the plunge pool increased to some 350m and
between 45-35m, respectively,
consistent with the magnitude of the specific discharges per chute and
operating head. Figure 2 depicts the
last measurements taken after the
raising of the reservoir to its Final Stage Headwater Elevation of 270.00
m.a.s.l. These results show that minimum bed contours appear at El. 75, in
front of Chute 1 which creates at this point a pool 55m deep. Results show
erosion up to 400 m downstream from the flip bucket. Measurements further show
that material recirculates within the pool depending upon the chute in
operation and its volume of discharge (Figure 3) but little net additional erosion
occurs. From the data it can be inferred
that the Plunge Pool is contained within a lenght in average some 2,2
times the acting Head difference and within a depth on the order of 0,3 times the
acting Head difference.
ENERGY DISSIPATION- DEVELOPMENT OF THE PLUNGE POOL-EROSION DATA
Figure 4 shows the record of energy dissipation
in the plunge pool during the time period studied. The curve shown on Figure 4
is self-explanatory and depicts a steep slope during the period 1979-1991
and flat slope from 1991-1992. During
the latter period spillway discharges were reduced substantially in contrast
with the 1979-1991 period. Eroded volumes in the river bed has been estimated
from the survey measurements and energy dissipation in the pool has been
calculated from detailed spillway operation records as indicated in Table 2.
When calculating the rock erosion volume, the lateral left bank erosion is not
considered. Data from 1994 soundings did not show significant additional
erosion. Estimates of power does not take into account other sources of energy
dissipation like water flow energy losses or energy loss of the water jet while
in contact with the air along its throwing distance, from the spillway exit to
the plunging point. Results indicate
that the most significant volume of river bed rock was eroded during the
time periods of May1983 -Nov 1984 and, June - Dec 1987 when associated averaged
power of the flow amounted to 3137 and 4822 MW and respective eroded estimated
volume resulted in 109000 and 65000 m3. Table 2 shows also that
although a maximum value of averaged energy of 5730 MW computed in the time
period of July 1988 - Feb 1989, only a reduced 22400 m3 of rock
appears to have eroded from the soundings. These figures which reflect
conditions in the field, show that even for the very large values of power, no
significant additional erosion takes
place. This is attributed to the deepening of the plunge pool. An estimation of
the Erosion Potential Index I (Kw/m3) combines both the Energy Dissipation in the pool (Kw) with volume
of rock eroded (m3). Both parameters are plotted in Figure 5 which
shows the evolution of the Erosion Potential Index. The similarity between the
1994 and 1991 measurements , and the very low values and the curve trend for
the value of I suggest that a stabilization condition of the pool exists
from1990.
CONCLUSIONS
-
Guri
Spillway has a formidable record of operation . Large flows have been spilled
by a single chute including the maximum discharge in Chute 1 which was
sustained for 100 days.The spillway discharges have created large pool erosion
with a total estimated volume of 400.000 m3. This material is deposited in
tailrace channel N° 1 . There is systematic evidence that large volumes of
eroded rock are recirculated inside the tailrace channel in correlation with
the operation of a given opened chute.
-
Spillway
discharges has been reduced significantly as a result of the increasing energy
generated by the two powerhouses, particularly since 1992.
-
The
pool has been developing according to the amount of energy dissipated. A 55m
deep and 400 m long pool exists now. Measurements indicate that the erosion
action has ocurred in the downstream direction and deposition takes place at
the toe of the main works protecting the foundation from erosion.
-
Energy
dissipation in the 1987-1991 period has been important and has configured the
plunge pool rocky bed to its lowest level .The 1991and 1994 sounding contours
remain similar after the 40.000 GWH energy dissipation which ocurred in the
1991-1994 period. This is attributed to the effect of the pool depth in
arresting the erosion capability of the flow.
REFERENCES
-
Castillejo
N., and Marcano A., "Operation of Guri Dam Spillway during Raising of the Dam",
Q63d, XVI Congress on Large Dams, San Francisco, 1988.
-
Castillejo
N., and Marcano A., "Raising of the Spillway Flip Buckets of Guri Dam", Seminar
on Energy Dissipation and Scouring in Hydraulic Structures Design, XXII IAHR
Congress, Lausane, 1987.
-
Marcano
G., A., Patiño A., Castro G., "Selection of the Energy Dissipators For the
Spillways of Lower Caroní Projects", Q63 - XVI Congress on Large Dams, San
Francisco 1988.

TABLE 2
GURI SPILLWAY PLUNGE POOL - ENERGY DISSIPATED -
EROSION
1979 - 1989





